Construction Projects

2019 Projects


US 2, Belknap Street Improvement Project
The Wisconsin Department of Transportation (WisDOT), in coordination with the City of Superior, has reconstructed US 2, Belknap Street, from Banks Avenue to Hill Avenue. This project replaced 1.4 miles of concrete roadway, upgraded the storm sewer system, and improved safety on Belknap Street. The project also included improvements on most of the connecting side streets north and south of US 2, Belknap Street, back to the respective alleys. Phase I of the reconstruction of the street was completed in November  2017 and Phase II will be fully completed in the spring of 2019.  Please click on the link for information and updates from WisDOT.    More Information

US 2/US 53, East 2nd Street Resurfacing Project
The Wisconsin Department of Transportation (WisDOT), in coordination with the City of Superior, is proposing resurfacing on East 2nd Street.  The project would be split into two separate construction seasons; 2020 and 2021.  
More information

Newton & Nelson Creeks Sewer Improvement Project
The City of Superior is addressing inflow and infiltration along Newton and Nelson Creeks. During significant wet weather events, sanitary sewers adjacent to Newton Creek (along 25th Avenue East right of way) and Nelson Creek (along 30th Avenue East right of way) become inundated by stream flow. This inflow increases flow throughout the sewers and overwhelms the system.
The project will significantly reduce infiltration and inflow to the Newton Creek & Nelson Creek trunk sewers by rehabilitating sewers and manholes, and by removing an above grade creek crossing. A new sewer is being installed in the 26th Avenue East Right-of-Way to further reduce flows to the Newton Creek sewer.
More information

Sidewalk Projects


 
The areas scheduled for 2019 sidewalk work are listed below.  If you are a homeowner in these areas, you will be receiving a letter further detailing the work and other important information about the project. 

Sidewalk replacement/spot repairs/pedestrian ramps
Logan Ave from N 16th Street to N 21st Street, west side
N 16th Street from Oakes Ave to Banks Ave, north side
Hill Ave from A Hayes Court to Laurel Ave, east side
Laurel Ave from Hill Ave to 6th Ave E, south side
6th Ave E from E 3rd Street to E 4th Street, southeast side
E 4th Street from 6th Ave E to 10th Ave E, southwest side
9th Ave E from E 5th Street to E 4th Street, northwest side
11th Ave E from E 5th Street to E 4th Street, northwest side
E 4th Street from 11th Ave E to 12th Ave E, both sides
12th Ave E from E 4th Street to E 3rd Street, northwest side
12th Ave E from E 6th Street to 100’ southwest, on the northwest side
E 8th Street from 15th Ave E to 17th Ave E, southwest side
E 7th Street from 15th Ave E to 16th Ave E, pedestrian ramps
E 6th Street from 15th Ave E to 18th Ave E, pedestrians ramps and spot repairs
E 5th Street at 15th Ave E and 17th Ave E, pedestrian ramps
15th Ave E from E 5th Street from E 4th Street, southeast side
16th Ave E from E 5th Street from E 4th Street, northeast side
E 4th Street from 15th Ave E to 17th Ave E, southwest side
16th Ave E from E 4th Street to E 3rd Street, southeast side
E 3rd Street from 15th Ave E to 16th Ave E, southwest side
N 16th Street from Cumming Ave to Baxter Ave, both sides
Harrison Street from Hammond Ave to Cumming Ave, both sides
Harrison Street from Cumming Ave to Baxter Ave, north side
Harrison Street from Baxter Ave to Lamborn Ave, south side
Cumming Ave from alley north of N 16th Street to N 17th Street, both sides
Baxter Ave from alley north of N 16th Street to Harrison Street, both sides
Baxter Ave from Harrison Street to N 17th Street, west side
Grand Ave from Lamborn Ave to Weeks Ave, southwest side
Weeks Ave from N 16th Street to N 18th Street, west side
Clough Ave from alley south of Belknap Street to N 16th Street, west side
F Street from E 2nd Street to E 5th Street, southeast side

Sidewalk Removals
2nd Ave E and E 4th Street in front of 109 E 4th Street, northeast side
Lackawanna Ave from N 22nd Street to N 23rd Street, east side

Here are maps of the areas where sidewalk work will be done:

F Street
UWS Area
2nd Ave East
Billings Park
East End 1
East End 2
Hill & Laurel
North 16th & Oakes

If you live in these areas, please be mindful of "no parking" signs being put up on the streets as this is an indication that work will begin soon in your area and access will be needed for both the crews and their equipment.

Once work begins in your area, crews will be setting up forms, and pouring the new sidewalks.  Once poured, the concrete needs to cure and harden for one week.  During this curing process it is important that the concrete not be driven on or heavily used.  This is especially important if you have a sidewalk crossing your driveway access.

Your cooperation and patience with us as we work is very much appreciated.  If you have questions regarding this matter, please contact the Engineering Department at: 715-395-7300.



Milling & Paving List



Asphalt milling is anticipated to begin in early June 2019 and Asphalt Paving Operations on about June 17.  Intended completion for this work is November 1, 2019.

The 2019 milling/paving list is posted below.

Asphalt Overlay:

Street Being Paved:

Starting at:

Ending At:

Elm Ave

N 12th

Winter

N 13th St.

Cedar

Elm

4th Ave E

E 5th

Tracks

21st Ave E

E 10th

E 11th

23rd Ave E

E 11th

E 12th

Banks Ave.

N 63rd

N 64th

Weeks Ave.

N 58th

Ballfield


Mill & Asphalt Overlay:

Street Being Paved:

Starting at:

Ending at:

Baxter Ave.

Belknap

N 13th

Fisher Ave.

Belknap

N 13th

N 14th St.

Fisher

Post Office Lot

N 14th St.

Grand

Cumming

N 14th St.

Ogden

Hughitt

Lamborn Ave.

N 21st

Belknap

Lincoln St.

Catlin

Fisher

N 19th St.

Weeks

Cumming

N 16th St.  

Lamborn

Hammond

N 22nd St.

Hughitt

John

N 20th St.

John

Ogden

N 17th St.

Tower

John

N 16th St.

John

Hughitt

John Ave.

N 16th

Belknap

Oakes Ave.

N 16th

N 18th

Hammond

N 21st

N 28th

N 19th St.

Lamborn

Baxter

E 18th Ave.

E 3rd St

E 9th St

21st Ave E.

Hill Ave

E 5th

Hill Ave.

Belknap

N 21st St.

N 63rd St.

Tower

Banks

John Ave.

N 62nd

N 64th




2019 Alley Paving

If your alley is scheduled to be paved in 2019, the petitions, maps and the costs to homeowners can be found by clicking on the alley below.  If you would like information about our alley paving program, please click on the "Street Division" tab on the left and you can read the policy and get a copy of the petition.  

A maximum of eight (8) alley blacktopping requests, received prior to June 30, will be accepted each year on a first-come, first-served basis.  Requests over that number will be processed for the following year.

1.  3rd & 4th Avenues East; between East 5th & East 6th Streets 

2.  North 7th & North 8th Streets; between Fisher & Clough Avenues

3.  North 19th & North 20th Streets; between Susquehanna & Wyoming Avenues 

4.  Pine & Elm Avenues; between North 13th & 14th Streets

5.  @ 3025 East 3rd Street (off 31st Avenue East)

6.  A & B Hayes Court; between Cedar & Hill Avenues

7.  44th Ave E to 45th Ave E, E 1st to E 2nd.